Bakum LNG filling station - construction work on the L 843
Temporary half and full closure of the junction (07.06. - 13.06.2021)
03.06.2021

Note: Construction work is being carried out on the L 843 road between the A1 Vechta junction and Molkenstraße.

 

Duration of the entire construction measure: 07.06.2021 - 13.06.2021

1.) Half-sided closure from 07.06.-11.06.2021

2.) Full closure of the intersection from 11.06. - 13.06.2021

 

1.) These works will only take place at night between 19.00 and 06.00.

1.) Damaged areas will be milled out and restored with mastic asphalt.

1.) The accessibility of the properties is given with mutual consideration.

 

2.) The work will take place from 11.06.2021 from 7.00 p.m. until 13.06.2021 at 8.00 a.m.

2.) Damaged areas will be milled out and restored with mastic asphalt.

2.) Access to the properties is only possible via a diversion.